The goods receipt is the moment purchasing turns into stock. It is the step most often done badly in companies coming from spreadsheets: goods are unloaded, the driver's delivery note is signed, and the paperwork waits on a desk until someone has time. Until the receipt is posted, the system thinks the goods are not there. Planners order them again, sales promises the wrong dates, and accounting cannot match the supplier's bill.
The rule is simple: post the receipt when the goods are unloaded, against the PO, for what you actually counted.
Count against the PO, not the delivery note
The supplier's delivery note says what they claim to have sent. The receiver's job is to count what actually arrived and compare it with what was ordered:
| Situation | What to do |
|---|---|
| Quantity matches the PO | Receive the full quantity |
| Less than ordered | Receive what arrived; the rest stays open on the PO |
| More than ordered | Receive up to the PO quantity; refuse or hold the excess until a buyer agrees a PO change |
| Wrong item | Do not receive it against this line; hold it and tell the buyer |
| Damaged | Receive and inspect, or refuse at the door, depending on policy |
Good practice is a blind count: the receiver counts without seeing the expected quantity first, then compares. It stops people from simply copying the number on the paperwork.
Partial receipts
Suppliers often deliver in several lots. Each delivery is its own receipt, adding to the received quantity of the PO lines. The PO stays open until everything has arrived, and the remaining quantity is visible to purchasing as an open order.
When the supplier will not deliver the rest, purchasing should close the remainder formally rather than leave it open forever: an old open PO line counts as incoming supply in MRP and as a commitment in the budget.
Inspection on arrival
For materials where quality matters (raw materials, safety items, anything a customer specifies), receipt and acceptance are two steps:
- Receive into a quarantine or hold location. The stock exists, but nobody can use it.
- Inspect against a checklist: dimensions, certificates of analysis, visual checks.
- Release the accepted quantity to the normal warehouse; reject the rest, which is returned to the supplier or scrapped.
This keeps bad material out of production while still recording, correctly, that the company now holds it. See Lots, serials and quality inspection.
Goods received not invoiced (GRNI)
Receiving creates an accounting entry even though no invoice exists yet. The company now owns the goods and owes the supplier for them. Receiving 100 units at Rp 50,000:
| Account | Debit | Credit |
|---|---|---|
| Inventory | 5,000,000 | |
| Goods received not invoiced (GRNI) | 5,000,000 |
When the supplier's bill arrives, it clears GRNI and creates the payable (see the three-way match). This is accrual accounting: the cost belongs to the month the goods arrived, not the month the invoice came. See Accrual vs cash accounting.
GRNI is also one of the best health checks in an ERP. Its balance should equal the value of recent receipts not yet billed. Old balances mean:
- bills that arrived but were never entered;
- receipts posted twice or for goods that never came;
- price or quantity disputes nobody resolved.
Review the GRNI ageing every month-end.
Lots, serials, bins and currency
Receive with all the detail the item needs, because it cannot be added later without corrections:
- Lot number and expiry for lot-tracked items, so you can pick first-expired-first-out and trace a recall.
- Serial numbers for serialised items, one per unit.
- Bin, when the warehouse uses bin locations.
- For foreign-currency POs, stock is valued in Rupiah at the exchange rate on the receipt date. A rate for that date must exist.
In Voltrus
What happens on receipt:
- Stock is added to the movement ledger at landed cost (the PO price plus this receipt's share of the freight), and the receipt posts Dr Inventory / Cr GRNI in Rupiah at the receipt date's rate. Under standard costing, inventory is booked at standard and the difference goes to the variance account.
- If a quality plan covers the item at the receipt point, the stock lands in the plan's hold warehouse and a pending quality inspection opens. Passing it moves the accepted quantity on; rejected quantity is scrapped with a write-off or moved to a reject warehouse.
- The PO's next step becomes Create supplier bill for the received, unbilled quantity.
There is no separate "partially received" status: each line shows how much of it has been received. A user who may only propose changes sends the receipt as a proposal, which appears in Approvals for a person to accept; connected AI agents work the same way.
The month-end checklist flags GRNI older than a set number of days.
Checklist
- Post receipts the same day goods are unloaded, by the person who counted them.
- Count blind where you can, then compare with the PO.
- Never receive more than the PO without a buyer's PO change.
- Set up quality plans for every item that needs inspection before use.
- Review GRNI ageing every month-end and chase anything older than 30 days.