Every purchase starts with two choices: who to buy from, and at what price. In spreadsheet companies both live in people's heads and email threads. The buyer knows which supplier is reliable and roughly what last time's price was; when the buyer is on leave, nobody knows. Sourcing in an ERP is about writing that knowledge down as master data, so the system can propose it and anyone can check it.
The supplier master
A supplier record is set up once and referred to by every PO, receipt, bill and payment. Get it right at the start, because errors in it repeat on every document.
The fields that matter most:
| Field | Why it matters |
|---|---|
| Legal name | Must match the name on their faktur pajak and bank account |
| NPWP and NITKU | Needed for PPN credit and for PPh withholding slips |
| PKP status | Only a PKP (VAT-registered business) may charge PPN |
| Payment terms | Drives the bill's due date and your payment run |
| Currency | The default currency of their POs |
| Lead time | Used by planning when nothing more specific is set |
| Bank details | Used by the payment run's bulk-transfer file |
One supplier, one record
Duplicate suppliers ("PT Maju Jaya", "Maju Jaya, PT", "MAJU JAYA") split the purchase history, break spend analysis and make double payment possible. Before creating a supplier, search for it. During migration, clean duplicates in the spreadsheet before importing (see Migrating from Excel).
Tax fields are not optional
Indonesian tax makes the supplier master part of compliance:
- A bill with PPN from a supplier that is not a PKP cannot be credited as input tax. Voltrus refuses PPN on a bill from a supplier not flagged as PKP.
- PPh 23 is withheld at double the rate when the supplier has no NPWP.
- PPh 26 on foreign suppliers uses the treaty (P3B) rate only while their DGT form is valid.
See PPh withholding.
Approved suppliers per item
Most items should have one or more approved suppliers, with one marked as the default. SAP calls this the source list or purchasing info record. It records:
- the supplier's own part number, so your PO says what their warehouse calls it;
- the supplier's lead time for this item, which is often different from their general lead time;
- which supplier MRP should propose by default.
Limiting buyers to approved suppliers is a quality control as much as a commercial one: a new supplier should pass some qualification (samples, a trial order, documents) before it appears on the list.
Prices: price lists, not memory
Agreed prices belong in the system, with validity dates. Then a PO line can be priced automatically and any deviation is visible. Good practice:
- One buying price list per supplier (or per supplier and currency).
- Quantity breaks where the supplier offers them (100+ units at a lower price).
- A valid from / valid to date, so a price increase starts on an agreed day rather than when someone remembers to type it.
Quotations and comparing them
For anything above a routine amount, or a new item, ask more than one supplier. The usual flow:
- Request for quotation (RFQ): the same specification, quantity and delivery date sent to two or three suppliers.
- Record each quotation as it comes in: price, quantity breaks, lead time, validity, payment terms.
- Compare on total cost, not unit price alone: freight, payment terms, lead time and the supplier's track record all count.
- Award to one supplier, convert their quotation into a PO, and mark the others rejected.
A worked comparison for 500 units:
| Supplier A | Supplier B | Supplier C | |
|---|---|---|---|
| Unit price | 48,000 | 46,500 | 47,000 |
| Freight | 0 (included) | 1,500,000 | 500,000 |
| Total landed | 24,000,000 | 24,750,000 | 24,000,000 |
| Lead time | 14 days | 10 days | 21 days |
| Terms | 30 days | Cash before delivery | 45 days |
Supplier B looks cheapest per unit and is the most expensive once freight is added. A and C tie on cost; A wins on lead time, C on terms. Keep the comparison with the award decision so an auditor can see why.
In Voltrus
A few things to know:
- Item suppliers do not carry a price. Prices live only on buying price lists. Keep them there so every PO line is priced from one place.
- There is no RFQ document that is sent to suppliers. Send your request by email as you do today, then record each reply as a supplier quotation.
- There is no side-by-side comparison screen yet. The API can rank open quotations for an item by unit cost and lead time, and an AI agent connected to Voltrus can run that for you; otherwise compare them in the quotation list filtered by item, and note the reason for the award in the quotation's discussion.
Checklist
- Clean and de-duplicate the supplier list before import; fill NPWP, PKP status and terms for every active supplier.
- Have bank-detail changes verified by phone and reviewed by a second person.
- Set a default supplier for every purchased item.
- Move agreed prices into buying price lists with validity dates.
- Require at least two quotations above an amount you set, and record them.